BOARD MEETING DATE: July 9, 2010
|
|
REPORT:
SYNOPSIS:
COMMITTEE:
RECOMMENDED ACTIONS:
Barry R. Wallerstein, D.Env. Background In the past CEQA lead agencies have approached the AQMD for information and guidance with regard to using emission credits as CEQA mitigation, primarily for construction air quality impacts. Although it is preferable that CEQA lead agencies identify onsite or local emission reduction mitigation measures using available low emission technologies, there is nothing to preclude them from using emission credits as CEQA mitigation. In response to these past requests, AQMD staff has developed a recommended procedure for using emission credits as CEQA mitigation. The following provides an overview of the procedure. Staff ensures that the project proponent and lead agency adhere as closely as feasible to the below-describes procedures.
Because the AQMD is not the Lead Agency for land development projects where emission credits may be used as CEQA mitigation, it is not responsible for approving the environmental document and/or Mitigation Monitoring Plan (MMP) in which the mitigation measure is required. However, the SCAQMD typically would have approval authority over a mitigation measure using emission credits to reduce regional air quality impacts, as well as enforcement and monitoring responsibility under the MMP. In accordance with Public Resources Code §21081.6, the MMP should outline the party responsible for implementing mitigation and the enforcement agency. Pursuant to CEQA Guidelines §15126.4(a)(2), to ensure that the mitigation measure is fully enforceable through a legally binding instrument, a Mitigation Agreement or other legally binding contractual instrument should be prepared. The Mitigation Agreement must be signed by the project proponent, the AQMD and the Lead Agency. The Department of Toxic Substances Control (DTSC) is the lead agency overseeing the cleanup and remediation of extensive amounts of hazardous substances at the former Ascon landfill in Huntington Beach. DTSC has entered into a consent decree and issued orders against a number of responsible parties to clean up the 38-acre hazardous waste site, which includes a variety of hazardous wastes, including “tarry” materials in five lagoons. Cleanup of the Ascon site will occur in phases. The first phase of the site cleanup is the Interim Removal Measure, which would consist of removing and disposing or recycling the tarry materials. DTSC has prepared a Mitigated Negative Declaration for the Interim Removal Measure plan, which includes mitigation measure AQ-3, consisting of using emission credits to mitigate significant construction NOx emissions. Without mitigation measure, AQ-3, construction NOx impacts would be significant and the Interim Removal Measure plan would be required to undergo an environmental impact report process, causing delays in remediating the site. The Interim Removal Measure Mitigated Negative Declaration was certified by DTSC on May 10, 2010. In accordance with the above procedure, the Department of Toxic Substances Control has submitted a Mitigation Agreement to the AQMD with regard to using emission credits as CEQA mitigation. Staff has reviewed the materials provided by DTSC and concluded that they have substantially followed the process established by AQMD staff. The Mitigation Agreement consists of a legally binding agreement to be signed by DTSC, AQMD’s Executive Officer, and the authorized representative of the Ascon Responsible Parties. Attachment
(DOC, 37k) |