BOARD MEETING DATE: October 8, 1999 AGENDA NO. 23




PROPOSAL:

Status Report on Major Projects for Information Management Scheduled to Start During First Six Months of FY 1999-2000

SYNOPSIS: 

Information Management is responsible for data systems management services in support of all AQMD operations. This action is to provide a status report for the current month on major automation contracts and projects to be initiated by Information Management during the first six months of FY 1999-2000.

COMMITTEE:

Not Applicable

RECOMMENDED ACTION:

Receive and file.

Barry R. Wallerstein, D.Env.
Executive Officer


Background

Information Management (IM) provides a wide range of information systems and services in support of all AQMD operations. IM’s primary goal is to provide automated tools and systems to implement Board-approved rules and regulations and to improve internal efficiencies. The annual Budget specifies projects planned during the fiscal year to develop, acquire, enhance, or maintain mission-critical information systems. As provided last July for the first six months of the fiscal year, Information Management is providing this report to detail major projects/contracts or purchases that are expected during the next six months.

Summary of Report

Attached is a report which identifies each of the major projects/contracts or purchases that are expected to come before the Board between July 1 and December 31, 1999. Information provided for each project includes a brief project description, FY 1999-2000 Budget, and the schedule associated with known major milestones (issue RFP/RFQ, execute contract, etc.).

Attachment(s)

Information Management Major Projects
for the Period July 1, 1999 through December 31, 1999

 

Item

Brief Description

Budgeted Funds ($)

Schedule of
Board Actions

Status

Computer Supplies Services

Pre-qualify vendors for purchase of computer, network, printer, and related services

$250,000

RFQ released 5/14; approve vendor list 7/9/99

Completed

HR/FIN System

Complete implementation services and enhancements to the New Integrated HR/Finance System

$130,000

Amend contract with Mikon 10/8/99

On schedule

Phone Switch Upgrade

Select vendor capable of upgrading the District’s phone switch automated call distribution (ACD) to be Y2K compliant.

$135,000

Release RFQ 7/9/99; execute contract 9/10/99

Completed

Telecommunica-tions Services

Select vendor(s) capable of providing all local and wide-area telecommunications services to the AQMD.

$756,400

RFQ released 6/11/99; execute contract 11/5/99

On schedule

Emission Reporting System

Select contractor to provide pri-vate data network services (PDN) to support the telecom-munication and data processing requirements associated with the Emission Reporting System (ERS) for RECLAIM.

$75,000

Approve release of RFP 8/13/99; execute contract 11/5/99

On schedule

Software Support Maintenance

Authorize PeopleSoft software support maintenance for the integrated HR/Finance System

$100,667

Authorize purchase 8/13/99

Completed

System Development Outsourcing

Add funding to the four system development outsource contracts to cover additional task orders for FY 1999-00. Tasks include the following:

  • Rule 1401 Toxics System Development
  •  Permit Streamlining Support
  • Compliance System Enhancements

To Be Determined

Amend contracts 11/5/99

Task orders on schedule

System Development Outsource RFP

Pre-qualify vendors to perform on-demand systems development services on a task-order basis.

$300,000

Release RFP 10/8/99; execute contract 2/11/00.

On schedule

 

 Shaded Columns - Activities completed
Double-lined Columns - Board Agenda items current for this month 

/ / /